Permission is granted to copy, distribute and/or modify this document under the terms of the GNU Free Documentation License, Version 1.2 or any later version published by the Free Software Foundation; with no Invariant Sections, no Front-Cover Texts, and no Back-Cover Texts. The license is available in "GNU Free Documentation License" homepage.


Table of Contents

1. General
Overall structure
Products and Test Plans
Test Case Categorization
Users
2. Test Specification
Creating Test Cases
Deleting Test Cases
Requirements relation
3. Keywords
Using keywords
Keyword Creation
Assigning Keywords
Filter by Keyword
4. Requirement based testing
Introduction
Availability
Requirements Specification
Requirements
Import requirements
Requirements to Test Case relation
Requirement based Report
5. Products
Overview
Creating new products
6. Test Plans
Creating a new Test Plan
Builds
Deleting TestPlans
7. Test Case Suite
Adding new Test Cases
Removing Test Cases from Test Case Suite
Priority
Ownership
8. Test Execution
General
Navigation
Filtering Test Cases
Define a tested build
Tree menu
Execution
Test Status
Insert Test results
Test Reports and Metrics
General Test Plan Metrics
Metrics of active Build
The Overall Build Status
Test Report
Blocked/Failed Test Cases
Total Bugs For Each Test Case
E-mail Test report
9. User Administration
Account settings
Role Permissions
User Roles
Rights Definitions
Test Plan Assignment

List of Tables

9.1. Role description
9.2. Product related Rights
9.3. Test Plan related Rights

List of Examples

4.1. Example of requirement coverage
8.1. TC colored according to the build
8.2. TC colored according to the latest result

Chapter 1. General

Overall structure

There are three cornerstones: Product, Test Plan and User. All other data are relations or attributes for this base. First, definition of a couple of terms that are used throughout the documentation.

Products and Test Plans

Product: A product is something that will exist forever in TestLink. Products will undergo many different versions throughout their life times. Product includes Test Specification with Test Cases and should be sorted via Keywords.

Test Plan: Test Plans are created when you'd like to execute test cases. Test plans can be made up of the test cases of one or many products. Test Plan includes Builds, Test Case Suite and Test Results.

Test Case Categorization

TestLink breaks down the test case structure into three levels components, categories, and test cases. These levels are persisted throughout the application.

Component: Components are the parents of categories. Each component can have many categories.

Category: Categories are the parents of test cases. Each category can have many test cases.

Test Case: Test cases are the fundamental piece of TestLink.

Test Specification: All components, categories and test cases within Product.

Test Case Suite: All components, categories and test cases within Test Plan.

Users

An User has a Role, that defines available TestLink features.

The next picture shows common activity according to user roles:

Chapter 2. Test Specification

Creating Test Cases

Tester must follow this structure: component, category and test case. At first you create component(s) for your product. You can fill description which can be printed then. Component includes categories. Category has the similar meaning but is second level of Test Specification and includes just Test Cases.

User can also copy or move Test Cases.

Test Cases has next parts:

  • Title: could include either short description or abbreviation (e.g. TL-USER-LOGIN)

  • Summary: should be really short; just for overview.

  • Steps: describe test scenario (input actions); can also include precondition and cleanup information here.

  • Expected results: describe checkpoints and expected behaviour a tested product or system.

Deleting Test Cases

Test cases, categories, and components may be deleted from a test plan by users with lead permissions from the "delete test cases" screen. Deleting data may be useful when first creating a test plan since there are no results. However, Deleting test cases will cause the loss of all results associated with them. Therefore, extreme caution is recommended when using this functionality.

Requirements relation

Test cases could be related with software/system requirements as n to n. The functionality must be enabled for a product. User can assign Test Cases and Requirements via link Assign Requirements in the main screen.

Chapter 3. Keywords

Using keywords

Keywords were created to give users another level of depth when categorizing test cases. Keywords serve as a collection of Test cases with some attribute within a Test specification. You can use it to define e.g.

  • Regression or Sanity set

  • Reviewed Test cases

  • Set of test cases valid for one platform

Keyword Creation

At this time keywords can only be created by users with the mgt_modify_key rights. These rights are currently held only by Leaders. Once a keyword or grouping of keywords have been created users may assign them to test cases.

Assigning Keywords

Keywords may be assigned to test cases either from the assign keyword screen (in batch) or via the test case management (individually).

Filter by Keyword

Users have the ability to filter by Keywords for:

  • Search Test Cases in Test Specification.

  • Add groups of Test cases in a Test case Suite (Test plan).

  • Execute test screen.

Chapter 4. Requirement based testing

Introduction

To proof that a system is build as specified, testers use requirement based testing. For every requirement, they design one or more test cases. At the end of the test execution a test manager reports on the tests that are executed and the requirements that are covered. Based on this information the client and the various stakeholders decide whether a system can be transferred to the next test phase or can go live. To ensure that a system is build as specified, test managers use a combination of risk and requiremetn-based testing to ensure that a system is build as specified from the customer and stakeholders perspective. As a result, this complete testing delivers the following advantages:

  • Linking risks and requirements will reveal vague or missing requirements. This is especially interesting for risks with a high priority.

  • Testing can be focused on the most important parts of an information system first: covering the risks with the highest priority.

  • Communicating in the same language as the client and the stakeholders. This makes it easier to report on the status of the test project. Beside that a better founded decision can be made whether to invest more in testing or take the risk.

  • The risks and their priority make negotiating on the test project in times of pressure easier. What risks have to be covered within this test project and which ones can be postponed. Risk and requirement-based testing results in a better controlled test project. The communication with the client and the stakeholders improved. The test manager begins testing with risks with the highest priority. The process is streamlined and the end result is higher quality.

Availability

The functionality is available on product level. I.e. Administrator should enable it for a specified product (Edit Product link in Main window). Otherwise links are not shown.

There are two user levels for this feature. The most of roles can view requirement but not modify. Refer to User section for more.

Requirements Specification

Requirements are bunched to one or more System/Software/User Requirement Specifications.

Create a document with Requirements:

  1. Click Requirements Specification in Main window. The List of Requirement Specification window is shown.

  2. Press Create button to create a document.

  3. Adjust Title, Scope and eventually Count of Test cases. The last parameter is used for statistics. Use only if you have a valid Requirement document but not all requirements are available at the moment in TestLink. Default value 'n/a' means that the current count of requirements in a specification is used.

  4. Press Create button to add data to database. You can see the title of your new created document in the table of List of Requirement Specification window.

  5. Click the title of document for next work. The Requirement Specification window is shown.

Each Requirement Specification has own statistics and report related to included data.

All Specification could be printed via Print button in the Requirement Specification window. Administrator can define company, copyright and confident text via configuration files.

Requirements

Each requirement has Title, Scope (html format) and Status. Title must not be unique and has max. 100 characters. Scope paramter is text in HTML format. Status can have vale VALID or NOT_TESTABLE. A NOT_TESTABLE requirements are not counted to metrics.

Requirements could be created/modified or deleted manually via TestLink interface or imported as CSV file.

Import requirements

TestLink support two types of CSV. The first 'simple' is composed from title and scope in each row. The second 'Export from Doors' try to detect header and chooses correct fields. Import compare titles and allow to solve conflicts. There are three ways: update, create requirements with same title and skip adding the conflicted ones).

Requirements to Test Case relation

Test cases are related with software/system requirements as * to *. I.e. you can assign more Test cases to one Requirement and more requirements could be covered by one Test Case. User can assign Requirements to Test Cases via the Assign Requirements link in the Main window.

A coverage of Test Specification could be view via pressing the button Analyse in the Requirement Specification window.

Requirement based Report

Navigate to Reports and Metrics menu. There is Requirements based Report link. Requirements in currect Requirement Specification and Test Plan are analysed for this report. All the latest result of test cases (available in Test Plan) are proceeded for each requirement. The result with the highest priority is applied for the requirement. Priority from the highest are: Failed, Blocked, Not Run and Passed.

Example 4.1. Example of requirement coverage

A requirement is covered by three Test Cases. Two of them are included in the current Test Suite. One passed and one was not tested for the Build 1. Now Requirement has overall result: Not Run. Second test case was tested with Build 2 and passed. So Requirement passed too.

Chapter 5. Products

Overview

Products are the cornerstone of TestLink. Products are releases of your company that may change their features and functionality over time but for the most part remain the same.

Creating new products

Create a new product is admin right. You cannot create products with the same name. You can assign a color of backgroung to product for a better lucidity.

Things to note when creating a new product:

  • Deleting Products themselves is not recommended from the system, because the deletion of products would either orphan lots of test plan cases or lead to their deletion.

  • Test Plans represent the testing of a product at a certain point of time. What this means is that All Test Plans are created from Product test cases.

  • TestLink has the ability to import your data into a product. Data is read in CSVs form and is explained further in the import section.

Chapter 6. Test Plans

Creating a new Test Plan

Test plans are the basis for test case execution. Test plans are made up of test cases imported from products at a specific point of time. Test plans can only be created by leads. Test plans may be created from other test plans. This allows users to create test plans from test cases that at a desired point in time. This may be necessary when creating a test plan for a patch. In order for a user to see a test plan they must have the propper rights. Rights may be assigned (by leads) in the define User/Project Rights section. This is an important thing to remember when users tell you they can't see the project they are working on

Builds

Builds are a specific release of software. Each project in a company is most likely made up of many different builds. In TestLink execution is made up of both builds and test cases. If there are no builds created for a project the execution screen will not allow you to execute. The metrics screen will also be completely blank. Builds currently cannot be edited or deleted.

Deleting TestPlans

Test plans may be deleted from the main page by users with lead permissions. Deleting test plans permanently erases the test plan and all of its corresponding data (test cases, results, etc). The deleting of data is a scary prospect and should be reserved to extreme cases. TestLink also allows users to deactivate test plans so that they no longer appear as a menu option.

Chapter 7. Test Case Suite

Adding new Test Cases

Test Case Suite is set of test cases which are defined to be run within Test Plan. Test case Suite is created via Add Test Cases from Test Specification to Test Plan. Test cases are added including Steps and Expected result. So, you must use 'Update modified Test Cases' page to update test scenario (version of test case).

Data from multiple products can be added into one test plan. Test Specification data can be filtered by keywords (adjusted in navigation pane).

Once data has been imported into a test plan it will be marked with checkmark. If a test case has already been imported it will be ignored if it is imported again.

Removing Test Cases from Test Case Suite

Test cases, categories, and components may be deleted from a test plan by users with Leader permissions from the "Remove test cases" page. Deleting data may be useful when first creating a test plan since there are no results. However, Deleting test cases will cause the loss of all results associated with them. Therefore, extreme caution is recommended when using this functionality.

Priority

TestLink gives users with Leader rights the ability to assign ownership and priority to test cases. General Risk/Ownership is done at the category level. TestLink currently does not allow users to assign risk or ownership at the individual test case level.

Risk levels are low, medium, high and Importance levels are 3, 2, 1. Users can rank the combinations of risk and importance (L1, L2, L3, M1, H2, M3, H1, H2, H3) as priority A,B,C.

Assigning risk, importance, ownership, and priority are all optional and will default to priority B in the metrics screen.

Ownership

Ownership affects both the execution and metrics screens. In the execution screen users have the ability to sort the executable test cases by the ones they have ownership of. In the main metrics screen there is a table that shows the remaining test cases by ownership. If there are no test case owners it defaults to none.

A Tester can also see a metrics of own executed tests in main page if these metrics are enabled (see Installation manual).

Chapter 8. Test Execution

General

Test execution is available when:

  1. A Test Specification is written.

  2. A Test Plan is created.

  3. Test Case Suite (for the Test Plan) is defined.

  4. A Build is created.

  5. The Test plan is assigned to testers (otherwise they cannot navigate to this Test Plan).

Select a required Test Plan in main page and navigate to the 'Execute tests' link. Left pane serves for navigation in Test Case Suite via tree menu, filtering and define a tested build.

Navigation

The navigation pane consists from a 'Filter & Settings' box and a tree menu with Test Case Suite.

Filtering Test Cases

This table allows the user to filter test cases for smart navigation before they are executed.

Owner: Users can filter test cases by their owner. Ownership is determined at the category level, is determined by leads, and can be changed at the Assign Risk and Ownership page under metrics.

Keyword: Users can filter test cases by keyword. Keywords are set either using the Create/Edit/Delete Test Cases or by the Assign Keywords To Multiple Cases. Keywords can only be created, edited, or deleted by leads but may be assigned to test cases by testers.

Result: Users can filter test cases by results. Results are what happened to that test case during a particular build. Test cases can pass, fail, be blocked, or not be run.

Define a tested build

Users can filter test cases by builds. Builds are the basic component for how test cases are tracked. Each test case may be run once and only once per build. Builds can be created by leads using the Create New Build page.

Tree menu

The tree menu in navigation pane includes Test Case Suite colored by results.

Menu colored: By default the tree will be sorted by the results for the defined build that is chosen from the dropdown box.

Example 8.1. TC colored according to the build

User selects build 2 from the dropdown box and doesn't check the "most current" check box. All test cases will be shown with their status from build 2. So, if test case 1 passed in build 2 it will be colored green.

Second possibility Last result is that menu is colored according to the latest test result.

Example 8.2. TC colored according to the latest result

User selects build 2 from the dropdown box and this time checks the "most current" check box. All test cases will be shown with most current status. So, if test case 1 passed in build 3, even though the user has also selected build 2, it will be colored green.

Execution

Test Status

Execution is the process of assigning a result (pass, fail, blocked) to a test case for a specific build. 'Blocked' test case is not possible to test for some reason (e.g. a problem in configuration disallows to run a tested functionality).

Insert Test results

Test Results screen is shown via click on an appropriate component, category or test case in navigation pane. The title shows the current build and owner. The colored bar indicate status of the test case. Yellow box includes test scenario of the test case.

The indication that the test case was updated or deleted in test Specification is not supported in 1.5 version.

Updated Test Case: Users will see the American flag if the original version of the test case (on the management side) has been updated. If users have the proper rights they can go to the update/delete test case page either through clicking on the test case number next to the flag or through the link on main page. It is not necessary for users to update test cases if there has been a change. They simply have the option of doing so if they wish.

Deleted Test Case: Users will see the "x" symbol if the original version of the test case (on the management side) has been deleted. If users have the proper rights they can go to the update/delete test case page either through clicking on the test case number next to the "x" or through the link on main page.

Test Reports and Metrics

The metrics pages sum up the results of execution into reports. Metrics are broken down by both individual builds and across all builds.

General Test Plan Metrics

This page shows you only the most current status of a test plan. For instance, you have test case 1 which was executed in builds 1,2, and 3. Build 1 2 3 Status Pass Fail Blocked Since the most recent result of the test case is blocked the result on the "Across All Builds" page would be blocked. If a user would go and change the status of build 3 to something else or not run the current result would be fail.

(in TL 1.0.4: View Project Status Across All Builds)

Metrics of active Build

This report shows the detailed results for a particular build defined in navigation pane.

(in TL 1.0.4: View Status by an Individual Build)

The Overall Build Status

View The Overall Build Status This report show a high level view of each build's result.

Test Report

View Status By Individual Test Cases This report shows each test case's result for every build. An user can navigate to Test Execution screen via link for each test Status.

Export to MS Excel is also available.

Blocked/Failed Test Cases

These reports show all of the currently blocked or failing test cases.

Total Bugs For Each Test Case

This report shows each test case with all of the bugs filed against it for the entire project.

E-mail Test report

Email Test Plan Info This page allows users to email the results of the entire test Plan or for a particular build. It also allows users to email the status of a component

Chapter 9. User Administration

Account settings

Every user on the system will also be able to edit their own information via the Account settings window (link Personal in menu bar).

TestLink allows users with administrator rights to create, edit, and delete users within the system. However, TestLink does not allow administrators to view or edit user's passwords. If users forget their passwords there is link on the login screen, that will mail the user their password based upon their user name and the email address they entered.

Role Permissions

TestLink is built with 6 different default permission levels built in. Changing of these rights is handled by the user administration link which is accessible by admins. These permission levels are as follows:

  • Guest: A guest only has permission to view test cases and project metrics.

  • Test Executor: A tester outside of the company that only has permissions to run tests allotted to them. (initially in 1.0.4 - otester)

  • Test Designer: A user can fully work with Test Specification and Requirements.

  • Test Analyst: A tester can view,create, edit, and delete test cases as well as execute them. Testers lack the permissions to manage test plans, manage products, create milestones, or assign rights. (initially tester, senior tester)

  • Test Leader: A lead has all of the same permissions as a Tester but also gains the ability to manage test plans, assign rights, create milestones, and manage keywords

  • Admininstrator: An admin has all of the same permissions as a lead but gains the ability to manage products

Note

Test plan related features needs also assign a Test Plan to be available. See Test Plan Assignment.

User Roles

There are predefined user roles. Adminstrator gives appropriate ability to modify data within TestLink. Each user has assigned just one of these roles.

If you view the table you will see rows for each of the permissions levels (guest ,tester, senior tester, leader, admin). The column next to the row holds all of the different rights levels which will be defined below. These levels have been determined as standard for the use but they are free to be edited or define a new roles (for experienced administrator). The user table contains a foreign key that points to the appropriate permission level in the rights table.

Table 9.1. Role description
Role List of Rights Ability
Guest mgt_view_tc, mgt_view_key, tp_metrics Browse data only.
Test Executor tp_execute,tp_metrics Execute test only.
Test Analyst tp_execute, tp_metrics, tp_create_build, mgt_view_tc, mgt_modify_tc, mgt_view_key, mgt_view_req Edit test Specification and execute tests.
Test Designer tp_metrics, mgt_view_tc, mgt_modify_tc, mgt_view_key, mgt_modify_req, mgt_view_req Edit Test Specification and Requirements.
Test Leader tp_execute, tp_create_build, tp_metrics, tp_planning, tp_assign_rights, mgt_view_tc, mgt_modify_tc, mgt_view_key, mgt_modify_key, mgt_view_req, mgt_modify_req All Test Plan right, edit test Specification and execute tests.
Administrator tp_execute, tp_create_build, tp_metrics, tp_planning, tp_assign_rights, mgt_view_tc, mgt_modify_tc, mgt_view_key, mgt_modify_key, mgt_view_req, mgt_modify_req, mgt_modify_product, mgt_users Everything possible. Only this role can maintain products and users.

Rights Definitions

Next tables list keywords used for definition of role abilities.

Table 9.2. Product related Rights
Right Description
mgt_view_tc Viewing Test Specification (data of component, category, and test case)
mgt_modify_tc Edit Test Specification (create,modify,delete,order, move, and copy components, categories, and test cases)
mgt_view_key Viewing keywords
mgt_modify_key Modifying keywords
mgt_modify_product Create,edit and delete products
mgt_view_req View requirements
mgt_modify_req Create,edit, associate and delete requirements
Table 9.3. Test Plan related Rights
Right Description
tp_execute Ability to execute test cases (insert test results)
tp_create_build Ability to create builds
tp_metrics Viewing metrics
tp_planning create, edit, delete Test Plans, assign risk/ownership, milestones, edit Tes Case Suite
tp_assign_rights Assigning the rights to view projects

Test Plan Assignment

Users can see only assigned Test Plans. In order to gain test plan permissions a user with lead or admin status must give them rights through the “Define user/project rights” link under “Test Plan Management”.

All users in the system will by default not have permissions to view newly created test plans (except for the test plan creator who can give themselves permissions at creation). Zero test plan permissions means that users will not see any Test Plans in the Test Plan dropdown box on main screen.

There is a table with Test Plan rights (i.e. which users can see which Test plan). This table is made up of a combined user id and project id. The main page contains code which checks to see if the logged in user has the appropriate permissions (and then shows the allowed projects. It is not recommended that this be hacked with.